Assign each cutover step, its evidence and the decision that allows the next step to start.

Use decision gates between dependent steps

Synthetic cutover sequence
StepOwnerEvidenceProceed only when
Freeze source changesBusiness leadFreeze time and pending-work listUsers know the fallback route
Final extractData operatorExport revision and row totalsBoundary matches the freeze
Import and reconcileMigration ownerAccepted/rejected totals and sample matchesCritical mismatches resolved
Open new systemRelease decision makerRecorded go decision and release versionAgreed acceptance tests pass
Download editable CSV ↓

Replace role labels with named people and add actual start/end times in the working file. Keep the fallback and rollback owner available for the window. A task’s planned time is not evidence that it completed.

Agree how to stop before starting

Example stop condition: accepted and rejected totals cannot account for the final extract. Hold opening the new system and inspect the difference. If users have already made new records, a rollback needs a reconciliation decision for those writes; switching the application version alone may be insufficient.

The import passes, but the named business approver is unavailable. What should happen?

Show the worked answer

Keep the agreed hold state or use a previously authorised substitute. Do not reinterpret technical success as business approval. Record the decision and actual decision maker.