Reconcile work completed during a system outage

Keep a controlled fallback register and match it to restored records before restarting automation.

Use one fallback register

Choose who may start fallback work and who may stop it. Give each task a temporary reference and record what was actually completed, including external confirmations. Do not mark a task complete merely because someone attempted it. The following example is a synthetic booking outage.

Fallback booking register
ReferenceRequested slotCompleted actionRestored system match
FB-ARoom A, 14:00–15:00Authorised duty lead confirmed the fallback booking under the outage policy; synthetic confirmation FB-CONF-ANo system record yet; reconcile the confirmed reservation
FB-BRoom A, 14:00–15:00Request received onlyDo not confirm; conflicts with FB-A
FB-CRoom B, 16:00–17:00Confirmation sent before outageBK-608 found; do not create again
Download editable CSV ↓

Reconcile before releasing the backlog

  1. Stop new fallback entries
  2. Match each reference
  3. Resolve conflicts and unknown outcomes
  4. Release only verified pending work

Keep unresolved items assigned to a reviewer while other verified tasks resume.

Record the last fallback reference and the restart time. Verify one successfully reconciled task and one conflict in the restored system. If an external action such as a message or payment already happened, the recovery plan must account for it; restoring a database does not undo that action.