Create an order from accepted quotation lines only

Keep accepted, declined and undecided lines visible without treating the full quote as won.

Capture the response at line level

Synthetic Q-74 permits independent line acceptance. Its three lines contain 5, 3 and 2 task units. The customer accepts the first, declines the second and has not answered the third. The order contains five units. The unanswered line remains open until a response or expiry; it is neither declined nor accepted. Store quote line IDs on the order so a later response can be explained.

Filled synthetic operating record
Quote lineOffered unitsResponseOrder units
L-A: setup5Accepted5
L-B: training3Declined0
L-C: follow-up2Unanswered0; pending response
Download editable CSV ↓

Confirm only the selected independent scope

  1. Identify revision and line IDs
  2. Record each response
  3. Check independent-line rule
  4. Create accepted-line order

A response saying only “go ahead” without identifying the selected scope needs clarification; do not infer all lines from an earlier discussion.

L-C is later accepted in time. What is the combined accepted quantity?

Show the worked answer

Seven units: five from L-A plus two from L-C. L-B remains declined. Link any additional order work to L-C rather than adding the entire quote again.

Units describe tasks, not prices. Independent acceptance is a fixture rule; linked bundles require a separate dependency check.