Cancellation is a set of work decisions
Synthetic O-177 cancellation affects setup S, report R and training T. S is complete, R is in progress and T has not started. The fixture preserves S’s evidence, requires a stop-and-save decision for R and removes T from the future schedule. Mark the cancellation requested first; it becomes operationally complete only when every work disposition is recorded. There is no automatic refund calculation.
| Work item | Current state | Cancellation disposition | Closure evidence |
|---|---|---|---|
| S | Completed | Retain completion record | Evidence S-7 kept |
| R | In progress | Stop and save agreed output | Stop decision pending |
| T | Unstarted | Remove future schedule | Schedule removal recorded |
Complete cancellation after item dispositions
- Record cancellation request
- Read every work state
- Assign stop, retain or remove action
- Close after evidence is present
An in-progress dependency must not be abandoned solely by changing the parent order label to cancelled.
S and T are resolved but R is pending. Is cancellation operationally complete?
Show the worked answer
No. R still needs a recorded stop-and-save result. Keep the cancellation in progress and name its owner.
This sheet excludes payment reversals, contractual cancellation rights and retention duties. Work states and closure rules are synthetic.