Count coaching time when assigning a trainee’s work

Allocate trainer and trainee effort separately so supported work does not consume invisible senior capacity.

Separate assisted work from trainer-only work

The synthetic trainer has six available hours. A trainee’s four-hour task requires two trainer hours under the supplied coaching plan. The trainer also has five hours of independent work queued. The trainee’s four hours cannot be treated as four extra senior hours or assumed to need no coaching.

Synthetic coaching workload
WorkTrainer hoursTrainee hoursPlan state
Assisted task24Reserved
Independent work5 requested; 4 fit01 hour unscheduled
Capacity total64No extra hours assumed
Download editable CSV ↓

Leave the unsupported hour visible

  1. Reserve two trainer hours
  2. Assign trainee’s four-hour task
  3. Allocate four independent trainer hours
  4. Defer or reassign the remaining hour

Reducing coaching requires an agreed revised support plan; simply removing its hours would change the conditions of the trainee task.

The trainer’s requested seven hours exceed six by one. The plan still needs the independent one-hour remainder, even if the trainee completes successfully. No competency or productivity guarantee follows from the allocation.

If another qualified colleague takes the last hour, what is the trainer’s final load?

Show the worked answer

Six hours: two coaching plus four independent. The other colleague owns one independent hour; the trainee still has four.