Resolve one worker’s conflicting allocations across projects

Compare named allocations with actual weekly availability and obtain an explicit reduction or reassignment.

Keep both projects in the capacity view

Synthetic worker Lin has twelve project hours this week after other assigned duties. Project A reserves eight and B seven. Task B includes a three-hour preparation unit that the supplied skills record allows Sam to take; Sam has four free hours. The plan does not assume additional working hours.

Synthetic cross-project allocation
WorkerBeforeApproved changeAfter / availability
LinA 8 + B 7 = 15Move B preparation 3 to Sam12 / 12 hours
Sam0 new project hoursAccept B preparation 33 / 4 hours
Download editable CSV ↓

Reassign the defined task, not an unnamed excess

  1. Combine both project allocations
  2. Identify three-hour excess
  3. Check preparation skill and Sam capacity
  4. Record accepted reassignment
  5. Update both project plans

If Sam cannot accept, Lin remains overallocated; show three unscheduled hours rather than deleting them from demand.

Lin keeps twelve hours and Sam takes three. Record the task reference so project B’s preparation has one current owner. The original fifteen hours of work remain in the plan across both workers.

How much unallocated capacity remains for Sam after accepting?

Show the worked answer

One hour: four available minus three assigned. Lin has zero spare project hours under this plan.