Change backorder priority before the pick starts

Record an authorised priority change and revise only allocations that have not entered physical picking.

Separate unpicked allocations from physical work

The sample receipt has five released units. O-W has three allocated but unpicked; O-X has two allocated and already picked. An authorised business decision gives O-Y priority for three. The supplied policy allows reassignment of unpicked allocations only; it does not authorise taking goods from an active pick.

Synthetic priority-reassignment record
OrderBeforeChange under PRI-YAfter
O-W3 allocated; unpickedRelease allocation 33 backordered
O-X2 allocated; pickedNo change2 remain in pick task
O-Y3 backorderedAllocate released 33 allocated; unpicked
Download editable CSV ↓

Make one visible reassignment

  1. Confirm authorised priority decision
  2. Check current pick state
  3. Release O-W unpicked allocation
  4. Allocate same three to O-Y
  5. Record affected orders and notify task owners

If O-W starts picking before reassignment is recorded, recheck custody and obtain a revised decision; the earlier unpicked assumption no longer applies.

PRI-Y retains the reason, authorised owner and affected order lines. It transfers a claim on three units; it adds no physical quantity. O-W’s backorder must reopen visibly so the team does not lose its demand. Customer communication remains a separate staff task, not an automatic message in this example.

Can O-Y receive all five units because it now has highest priority?

Show the worked answer

No. The approved change covers the three unpicked units. O-X’s two picked units remain assigned; O-Y receives three and O-W reopens for three.