Review the impact of a software scope change

Trace a proposed change through data, permissions, tests, content and operating work before approving it.

Follow one change through the whole task

Synthetic proposal: let staff reschedule a booking rather than cancelling and recreating it. The old baseline has cancellation only. The change is not yet approved; no price is assumed.

Filled synthetic worksheet; editable CSV
Affected areaNew decision/workOwnerEvidence before approval
Record identityPreserve booking ID through the moveData ownerBefore/after synthetic record
Permission and conflictWho may move, and what happens if new room is occupied?Operations ownerAllowed/denied/conflict cases
Messages and staff guideNew status, bilingual message and handling procedureContent and training ownersReviewed wording and walkthrough
Download editable CSV ↓

Small interface changes can affect other work

The supplier says rescheduling adds just one button. Is that enough information to approve the change?

Show the worked answer

No. Resolve identity, authority, conflicts and communication shown in the sheet, then review the revised effort and scope. Button count does not establish the complete change.

This is an impact review, not a pricing formula or automatic authorisation. The change record should link to the original baseline and actual approving decision.