Project decision and rationale register

Keep the evidence, rejected alternative and review trigger beside an approved project decision.

Record what would change the decision

Synthetic project: a centre chooses manual refund review for its first booking release. The project sponsor can approve scope; finance owns refund decisions. These rows are invented decisions, not evidence of a delivered system.

Filled synthetic worksheet; editable CSV
Decision referenceDecision and authorityReason and alternativeReview trigger
D-11Keep staff refund approval; sponsor approvedRefund policy is incomplete; automatic approval deferredFinance publishes a complete approved policy
D-12Use one launch branch; sponsor approvedSecond branch has no confirmed opening dateOpening date and branch owner confirmed
D-13Replace D-12 with two-branch pilot; not approvedProposal received; dependency still unresolvedSponsor decision after branch evidence
Download editable CSV ↓

A proposal does not supersede an approval

Does D-13 make D-12 obsolete?

Show the worked answer

No. D-13 is unapproved. Keep D-12 active, link the proposal to it and record the approver and evidence if a replacement is accepted.

A decision log preserves reasoning and status. It does not create contract authority or replace the agreed scope document. References and approval states here are illustrative.