Record the assumptions behind a delivery estimate

Tie each estimate assumption to evidence, an owner and a condition that requires re-estimation.

Make uncertainty visible without inventing a price

An invented project estimate assumes one source export, two user roles and customer-supplied bilingual copy. No labour rate, price or promised completion date is supplied.

Filled synthetic worksheet; editable CSV
AssumptionEvidence/statusOwnerRe-estimate when
One CSV source with stable IDsSample received; full export not checkedData ownerA second source or conflicting IDs appear
Two roles: staff and adminRole list approved in fixtureBusiness ownerA third role needs different permissions
Customer supplies reviewed EN/zh-HK copyDrafts only; approval pendingContent ownerTranslation or repeated rewrites enter supplier scope
Download editable CSV ↓

A changed assumption needs an impact review

A second source file is discovered. Does this sheet tell you how many extra days to add?

Show the worked answer

No. It identifies the broken assumption and relevant owner. Inspect overlap, formats and work before revising the estimate; do not automatically double time or price.

The sheet records estimate conditions, not a quotation or guaranteed timeline. Keep original and revised assumptions alongside any real proposal.