Continuous appointments or staged resource use?

Separate service elapsed time from the time each resource is occupied.

Download complete case notes and answer keys ↓

Compare the operating models

A synthetic colour service uses staff+chair for twenty minutes, chair only for thirty, then staff+chair for ten. The customer is present for sixty minutes but active staff work totals thirty.

Filled decision worksheet
Business requirementOne continuous blockStage-specific occupation
0–20 minutesStaff+chair occupiedPreparation: staff+chair
20–50 minutesStaff still blockedProcessing: chair only
50–60 minutesStaff+chair occupiedFinish: staff+chair
Download editable CSV ↓

Work through the chosen model

Stage records name offset, duration and required resources. The customer appointment retains the full start/end. Staff availability follows assigned stages only if the system and operating practice can reliably keep the return stage; otherwise reserve the safer continuous block under supplied policy.

  1. Choose the full service time
  2. Allocate stage resources
  3. Return staff for the finish stage

Stages can reflect real operations but are harder to maintain when durations vary. Ask the supplier to demonstrate the return stage before accepting a staged model.

A 10:00 start occupies the chair to 11:00. Staff are assigned 10:00–10:20 and 10:50–11:00. The middle gap is not automatically a sellable thirty-minute appointment including travel or preparation.

When the other model fits

Staff must supervise continuously during processing. Still release the middle stage?

Show the worked answer

No. The actual dependency is continuous staff occupation.