Review dependent tasks when an order date moves

Recalculate a small dependency chain instead of shifting only the visible customer appointment.

Use offsets from the agreed delivery event

Synthetic order O-188 completes on 30 October. Data approval is due four calendar days before completion; preparation is due two days before. Moving completion to 2 November gives new due dates of 29 and 31 October. Already completed tasks keep their actual dates. Any unfinished prerequisite without an owner prevents schedule confirmation, even if the customer-facing completion date has been changed.

Filled synthetic operating record
TaskOffsetOriginal dueNew due
Data approvalCompletion minus 4 days26 October29 October
PreparationCompletion minus 2 days28 October31 October
CompletionAnchor event30 October2 November
Download editable CSV ↓

Confirm the whole dependent schedule

  1. Read proposed anchor date
  2. Calculate prerequisite due dates
  3. Check owners and task states
  4. Confirm or hold the revised schedule

Working-day calendars, unavailable staff and external deadlines are not included; do not imply the calculated dates prove capacity.

Does moving completion three days later move each unfinished offset task by three days?

Show the worked answer

Yes under this fixed calendar-offset fixture: 26 to 29 October and 28 to 31 October. Feasibility still needs review.

The offsets are synthetic scheduling rules. This differs from booking capacity and does not reserve staff or resources.