Review queue capacity planner

Model daily arrivals, whole-item reviewer capacity and the waiting work at each day’s end.

Whole items stay with one reviewer. New items arrive before processing each working day. Enter working days, not calendar dates.

Daily capacity 36 items; ending backlog 0 items.

Daily whole-item capacity
36
Backlog at horizon end
0
First empty end-of-day queue
Day 7
Backlog from the initial state to the final day; the table previews up to 60 days and export includes every value.
First 60 planning days at most; export includes the full horizon
DayOpeningArrivalsProcessedEnd
1100203684
284203668
368203652
452203636
536203620
62020364
7420240
8020200
9020200
10020200

Count whole items per reviewer

The planner treats each item as work completed by one reviewer. It first divides each reviewer’s available minutes by the minutes per item and rounds down, then multiplies by the number of reviewers. Unused fragments of different people’s time are not pooled into another completed item. Minutes accept tenths; staffing and work counts are whole numbers.

Synthetic daily-capacity example
Input or resultValue
Reviewers2
Minutes per reviewer per day180
Minutes per whole item10
Whole items per reviewer18
Daily team capacity36 items
Download editable CSV ↓

Two reviewers each have seven minutes; one item takes twelve minutes and cannot be split. Is capacity one item?

Show the worked answer

No. Each reviewer has capacity floor(7 ÷ 12)=0, so the team completes zero whole items. Aggregating fourteen minutes would violate this model’s one-reviewer-per-item rule.

Add arrivals before the day’s work

New items arrive before processing on each modelled working day. Available work is opening backlog plus arrivals; processed work is the lesser of available work and daily capacity. The remainder carries to the next day. The graph includes the initial backlog at day zero and the end-of-day balances.

Opening backlog 100; daily arrivals 20; capacity 36
DayOpeningArrivalsProcessedEnd
1100203684
62020364
7420240
Download editable CSV ↓

Under the example, is the queue empty at the end of day six?

Show the worked answer

No. Four items remain at day six. Day seven begins with four, receives twenty and processes twenty-four; it is the first empty end-of-day queue.

These are constant planning assumptions, not a prediction of real attendance or completion speed. Days are working days you define; holidays, absence, priority changes and varying task duration are outside this model. Recheck the inputs against measured operations before scheduling staff. If daily arrivals exceed capacity, the backlog grows even with a low initial balance.