Track external dependencies before a project launch

Connect an outstanding customer or third-party input to the blocked delivery task and its next decision.

Name the blocked task and owner

Synthetic launch L-3 needs an approved domain setting, a reviewed data sample and sign-off on reminder text. Dates are project discussion fields; the sheet contains no promised delivery date.

Filled synthetic worksheet; editable CSV
DependencySupplier of inputBlocked taskNext decision if absent
Domain-setting authorityCompany domain ownerConnecting the agreed live hostnameKeep test environment; escalate access decision
Reviewed data sampleData ownerChecking full import mappingDo not replace with invented production facts
Reminder wording approvedContent ownerEnabling customer reminderDecide whether reminder can be deferred
Download editable CSV ↓

A dependency is not always a whole-project blocker

Reminder wording is pending. Does the worksheet prove the entire project must stop?

Show the worked answer

No. It identifies the reminder task as blocked. The authorised owner decides whether that task can be deferred while other accepted work continues; do not silently enable unapproved wording.

This is dependency tracking, not a critical-path algorithm or a guarantee that delay can be absorbed. Any revised launch scope or date needs actual impact review.