Record the decision to proceed with a migration cutover

Keep agreed decision conditions, evidence gaps and the authorised choice separate from the step-by-step cutover plan.

Use decision gates rather than a readiness score

This invented pilot requires matching source/target counts, no unresolved required-field errors and a receiving owner who has reviewed recovery evidence. Evidence CUT-7 contains the supplied count/error review; REC-2 is the supplied recovery-drill record. Cutover owner Kai alone decides. The fictional scope is the 100-row pilot snapshot only, excluding live operation and customer messaging. The last row records Kai’s decision at 10:00 on 10 October 2026, not a real cutover.

Filled synthetic worksheet; editable CSV
Decision conditionSynthetic evidenceCondition statusFollow-up owner
Counts reconcileCUT-7: 100 source rows; 100 target rowsCount condition met onlyData owner checks values too
Required-field errors resolvedCUT-7: one row still has no customer IDNot metSource owner corrects it
Recovery evidence reviewedREC-2 exists; receiver has not reviewedUnconfirmedReceiving operations owner
Decision: Kai, 2026-10-10 10:00Defer on CUT-7/REC-2: customer ID and recovery review unresolved100-row pilot only; live/messages excluded; no proceed authoritySource corrects; receiver reviews; Kai reconsiders on updated evidence
Download editable CSV ↓

One green condition does not close the decision

Counts match at 100. Does this fixture support proceeding now?

Show the worked answer

No. Kai’s recorded choice at 2026-10-10 10:00 is defer because the required customer ID and recovery review remain unresolved. Obtain both pieces of evidence and Kai’s revised decision before proceeding; matching counts cannot override that choice.

Meeting this checklist is not a production-safety certification. Use the existing cutover run sheet for execution and the actual recovery and decision conditions for your system.