Recorded effort and a local remaining-work draft

Inspect spent and remaining hours independently, with an editable draft that leaves the recorded forecast intact.

Illustrative effort record; editable fields are local drafts.

Download complete case notes and answer keys ↓

Keep recorded and draft estimates distinct

Synthetic T-191 has six actual hours and four recorded remaining hours, forecast ten. The original estimate was eight. A local number draft starts at four with nonnegative half-hour steps; it does not recalculate or save the recorded forecast.

Filled preview acceptance sheet
Input or inspectionExpected viewBusiness meaning
Read recorded forecast6 actual +4 remaining =10Original8 retained separately
Enter −0.5 or 0.25Input constraint invalidNonnegative half-hour steps
Edit draft to3Draft3; recorded remainder4Recorded forecast still10
Download editable CSV ↓

Inspect effort, forecast and draft separately

  • Recorded totals are table values rather than editable inputs.
  • Draft constraints are text-linked to the number field.

How far above the original estimate is the recorded forecast?

Show the worked answer

Two hours: ten minus eight. The draft input does not change that recorded comparison.

Actual work hours are retained rather than overwritten by a new planning assumption.