Fit a critical restore scope inside a rehearsal budget

Add setup, restore and verification durations before accepting a timed recovery plan.

List mandatory and deferred work

Synthetic rehearsal budget is 60 minutes. One operator executes setup 8, critical DB restore 25 and critical journey verification 12 sequentially. Archive restore 20 may be deferred; it is not required for the critical journey. Durations are supplied estimates, not measured performance.

Restore scope budget
TaskMinutesScope
Setup8Required
Critical DB25Required
Journey verification12Required
Archive20Deferrable
Download editable CSV ↓

Calculate the sequential critical path

  1. Include setup and verification
  2. Sum mandatory sequential work
  3. Compare full and critical scope

No task may be treated as parallel without a supplied worker/dependency plan.

What fits 60 minutes and how much headroom remains?

Show the worked answer

Critical scope totals 45, leaving 15 minutes. Full scope totals 65 and exceeds budget by 5. Critical completion must explicitly leave the archive pending.

Preserve deferred scope in the decision

Filled decision checks
CaseDecisionReason
Critical onlyFits 45 min15 min headroom
All four tasksDoes not fit 65 min5 min over
Download editable CSV ↓

Use the rehearsal to record actual durations and verified task output. A calculated fit is not an achieved restoration-time claim.