Order feasibility checks by their expected stopping effort

A more expensive first check can save work if it stops unsuitable plans sooner.

Plan from the supplied facts

The fictional plan proceeds only if independent checks A and B both pass. A costs 2 hours and passes with probability 0.5; B costs 1 and passes with probability 0.9. Stop immediately on failure. Probabilities and perfect check results are original model assumptions.

Editable original planning example
OrderFirst check costChance second neededExpected total h
A then B20.52 + 0.5×1 = 2.5
B then A10.91 + 0.9×2 = 2.8
Both always3 total13
Download editable CSV ↓

Work through the choice

Only the first pass probability controls whether the second check is performed. Choosing by first-check price alone ignores the chance of stopping.

Which order has lower expected effort, and by how much?

Show the worked answer

A then B: 2.5 versus 2.8, saving 0.3 expected hours. An individual completed inquiry may still use all three hours.

Material to use in your plan

For each proposed order, record first cost + first pass probability × second cost. Include conditional probabilities or further branches if the checks are not independent.