Calculate expected effort for mutually exclusive routes

Keep a weighted planning average separate from any single route.

Effort for exclusive routes

Routes are exclusive and exhaustive; percentages must total 100. Zero-weight routes are excluded from possible outcomes.

Exclusive routes

Hours: 0–10000, at most two decimal places.

RouteProbability %Conditional hours
Short route
Long route
Third route

Default case shown. Editing requires JavaScript.

Weighted hours
RouteProbability %Conditional hoursWeighted hours
Short route7521.5
Long route2582
Third route000
Expected hours
MeasureHours
Expected hours3.5
Possible route outcomes (hours)2 / 8

Plan from the supplied facts

The fictional model supplies two mutually exclusive, exhaustive routes: 75% probability of 2 hours, 25% of 8 hours. These probabilities are teaching inputs, not measured forecasts. Expected effort is the probability-weighted sum; no actual route takes 3.5 hours in this model.

Editable original planning example
RouteProbabilityHoursWeighted hours
Short0.7521.5
Long0.2582
Total1Either 2 or 83.5
Download editable CSV ↓

Work through the choice

0.75×2+0.25×8=3.5 is an average over the supplied model. A promise to finish within 3.5 hours would fail whenever the long route occurs.

If the long-route probability becomes 0.5, keeping the two route hours fixed, what is expected effort?

Show the worked answer

0.5×2+0.5×8=5 hours. The possible realised outcomes remain 2 and 8 hours.

Material to use in your plan

Use one row per exclusive route with probability, conditional hours and product. Require probabilities to sum to one; show possible outcomes beside the expected value.