Replan remaining work around a supplied nonworking day

Use the project’s explicit work calendar when converting remaining effort into a finish date.

List the actual working slots

The synthetic team has six hours of remaining work and a daily capacity of three hours. Day 1 and Day 3 are working days; Day 2 is a declared project closure. These are invented calendar labels, not public-holiday claims. The task cannot run unattended on Day 2.

Synthetic work-calendar allocation
DayCapacityAssignedRemaining after day
Day 13 hours3 hours3 hours
Day 20 hours; closure0 hours3 hours
Day 33 hours3 hours0 hours
Download editable CSV ↓

Move effort to the next authorised slot

  1. Confirm remaining effort
  2. Load supplied closure calendar
  3. Allocate only working capacity
  4. Record finish on Day 3

If Day 3 availability is unconfirmed, show the final three hours as unscheduled rather than declaring a finish date.

The six hours span three calendar days but two working days. Keep the closure visible beside the revised finish so another planner does not restore the invalid Day 2 assignment.

If remaining work becomes seven hours with the same three-day calendar, is Day 3 enough?

Show the worked answer

No. Day 1 and Day 3 supply six hours, leaving one hour for a later confirmed working slot.