List the actual working slots
The synthetic team has six hours of remaining work and a daily capacity of three hours. Day 1 and Day 3 are working days; Day 2 is a declared project closure. These are invented calendar labels, not public-holiday claims. The task cannot run unattended on Day 2.
| Day | Capacity | Assigned | Remaining after day |
|---|---|---|---|
| Day 1 | 3 hours | 3 hours | 3 hours |
| Day 2 | 0 hours; closure | 0 hours | 3 hours |
| Day 3 | 3 hours | 3 hours | 0 hours |
Move effort to the next authorised slot
- Confirm remaining effort
- Load supplied closure calendar
- Allocate only working capacity
- Record finish on Day 3
If Day 3 availability is unconfirmed, show the final three hours as unscheduled rather than declaring a finish date.
The six hours span three calendar days but two working days. Keep the closure visible beside the revised finish so another planner does not restore the invalid Day 2 assignment.
If remaining work becomes seven hours with the same three-day calendar, is Day 3 enough?
Show the worked answer
No. Day 1 and Day 3 supply six hours, leaving one hour for a later confirmed working slot.