Add approved scope to the work queue without marking it started

Translate an approved addition into named tasks, prerequisites and capacity before changing active status.

Turn the decision into executable tasks

Synthetic decision CH-A approves a four-hour export addition. It needs a one-hour field definition followed by three hours of implementation. The field owner has one hour today; the implementer has only two hours tomorrow. Approval grants scope but does not create the missing implementation hour.

Synthetic approved-scope work queue
TaskEffort / prerequisiteAssigned slotState
DEF-A1 hour; CH-AToday / owner MeiReady
IMP-A3 hours; DEF-A complete2 tomorrow; 1 unscheduledQueued
CH-A scope4 total hours3 placed; 1 unplacedApproved; not completed
Download editable CSV ↓

Track the addition through readiness and allocation

  1. Link new tasks to CH-A
  2. Sequence DEF-A before IMP-A
  3. Reserve confirmed capacity
  4. Leave missing hour unscheduled
  5. Start implementation only with ready fields

If implementation cannot be split, the two-hour slot cannot begin the three-hour task under that rule; obtain a continuous slot.

The approved addition becomes two tracked tasks rather than an automatic completed milestone. Preserve the original work plan and add these allocations explicitly, so existing tasks are not silently displaced.

Can CH-A be marked completed after DEF-A finishes?

Show the worked answer

No. One hour is complete and three implementation hours remain, including one still unscheduled.