Transfer the work context with the role
In this invented handover, Ren leaves the integration lead role and Sol takes over. Ren holds two open clarification questions and a draft connector change; the company still owns scope decisions.
| Transfer item | Synthetic current state | Receiving evidence |
|---|---|---|
| Open questions | Q-4: required status; Q-5: correction rule | Sol can identify owner and status for both |
| Draft work | Connector change C-8 not approved | Draft and baseline linked; approval remains pending |
| Approved test access | Ren’s individual access not shared | Sol receives authorised access and Ren removal decision recorded |
A new lead does not reset prior decisions
Sol wants to implement C-8 immediately because Ren drafted it. What is still missing?
Show the worked answer
Approval remains pending. Transfer the draft context and obtain the existing decision owner’s choice before implementation; personnel replacement does not approve scope.
This is a continuity review, not a claim that a contract permits or prohibits substitution. Confirm actual role, authority and access arrangements separately.