Plan reviewer availability across project decisions

Match review effort to the available people and time window before promising concurrent milestones.

Count the reviewing work, not just meetings

Original synthetic window: Mei has two hours on Tuesday for reviews. The data sample needs 90 minutes and bilingual page review needs 60 minutes. These are invented effort assumptions, not measured rates.

Filled synthetic worksheet; editable CSV
ReviewRequired reviewer/timeAvailable windowPlanning result
Data sampleMei; 90 minutesTuesday shared 120 minutesFits alone; consumes 90
Bilingual page contextMei; 60 minutesSame Tuesday 120 minutesCombined demand 150 exceeds 120 by 30
Potential reassignmentRen can review English only in fixtureRen has 60 minutes; zh-HK still MeiReview actual split before assuming full relief
Download editable CSV ↓

Do not double-book a decision owner

Can both original reviews finish inside Mei’s two-hour window without a changed plan?

Show the worked answer

No. 90 + 60 = 150 minutes, 30 more than 120. Prioritise, extend the window or agree an appropriate reassignment; Ren’s English availability does not automatically cover Chinese review.

This is a small capacity check for supplied assumptions, not a project scheduling optimiser. Unexpected work, different skill levels and interruptions require a revised plan.