Match each claim to an environment
The fictional project has Demo D, Test T and Live L. A supplier can demonstrate synthetic reminders in D; company approval for live recipients in L is not yet provided. No provider connection is asserted.
| Environment | Data/action scope | Needed evidence/authority | Claim allowed in fixture |
|---|---|---|---|
| Demo D | Invented records; simulated reminders | Synthetic scenario and visible result | Demo behaviour shown only |
| Test T | Approved test recipients only | Test access and recorded delivery attempt | Test result under T conditions |
| Live L | Real customer operation | Explicit live scope, access and release decision | Not complete from D or T evidence alone |
A test message is not permission to contact customers
The demo reminder worked. Can the supplier enable Live L customer reminders now?
Show the worked answer
No. The fixture’s live recipients and release authority are pending. Retain the demo result, complete live prerequisites and obtain the release decision.
This describes agreed environment boundaries, not vendor capabilities or blanket permission for test or live sends. Real actions require the project’s actual authorisation.