Find the remaining-use horizon that justifies a method switch

Solve the equality before applying a lower recurring effort claim.

Plan from the supplied facts

Original method needs four hours per future run. Proposed method needs six transition hours once and two hours per future run. Future run count n is a nonnegative whole number; historical work is outside both future totals. Switching is lower effort only when 6+2n<4n.

Editable original planning example
Future runsStay hSwitch hLower effort
2810Stay
31212Tie
41614Switch
Download editable CSV ↓

Work through the choice

The six-hour transition is recovered by three runs saving two hours each, but that is only a tie. Strict savings start at the fourth whole run.

For five future runs, what is the effort saving from switching?

Show the worked answer

Stay 4×5=20; switch 6+2×5=16; saving four hours.