Separate one-off effort from work per item

Use an effort equation that changes correctly with volume.

Shared setup and repeated work

Setup is shared once. Hours describe effort, not a finish date.

Effort inputs

Hours: 0–10000, at most two decimal places.

Default case shown. Editing requires JavaScript.

Total
ComponentHours
One-off setup hours4
Repeated work hours6
Total10

Plan from the supplied facts

Original fictional plan: preparation takes 4 hours once, then each of n independent record types takes 2 hours. Total effort is 4+2n, with no elapsed-date promise. Repeating the preparation inside every item estimate would describe a different plan.

Editable original planning example
Record types nOne-off hoursItem hoursTotal hours
1426
34610
541014
Download editable CSV ↓

Work through the choice

The slope is 2 hours per added type; the 4-hour intercept is retained even when n changes. State whether preparation is genuinely shared before using this equation.

The scope rises from three types to five. How many extra hours are estimated?

Show the worked answer

4 hours: (4+2×5)−(4+2×3)=14−10. The one-off preparation cancels in the difference.

Material to use in your plan

Use columns one-off task, repeat unit, unit count, hours per unit and total. Write E(n)=F+vn beside the worksheet, with the scope under which F remains shared.