Choose a first slice that completes one user path

Compare a usable narrow slice with unfinished layers.

Plan from the supplied facts

Fictional user path requires entry UI, rule processing and record storage together. Estimated effort is 1,2,2 hours respectively. A separate display-only UI costs 1 hour but completes no user path. All components are proposed work; the table evaluates a plan, not an implemented product.

Editable original planning example
SliceIncluded workHoursComplete user paths
UI layerEntry + display UI20
Partial pathEntry + rules30
Narrow complete pathEntry + rules + storage51
Download editable CSV ↓

Work through the choice

Completed layer count cannot substitute for a completed user path. The five-hour slice covers less breadth than a full product but closes the stated chain.

Does a three-hour entry-and-rules plan provide the stated complete path?

Show the worked answer

No. Storage is missing. The least listed complete path needs 1+2+2=5 hours.

Material to use in your plan

Draw one user path across entry, processing and durable outcome, then mark which proposed slice includes each part. Count completed paths separately from completed layers.