Reconcile a top-down effort allowance with item estimates

Expose unallocated effort instead of inventing a task to use the balance.

Plan from the supplied facts

Original planning allowance is 48 hours. Independently estimated interface work is 28 hours and record work 16 hours. The allowance and the item estimates answer different questions. Their difference is an unallocated 4 hours, not an automatic contingency entitlement or a completed work item.

Editable original planning example
EntryHoursMeaning
Allowance48Top-down limit
Estimated items28 + 16 = 44Known item total
Difference4Unallocated
Download editable CSV ↓

Work through the choice

Do not scale every task upward merely to make the sum equal the allowance. First decide whether a missing task, protected reserve or unused allowance explains the difference.

Another independently estimated item is 6 hours. What is the reconciled position?

Show the worked answer

Items total 50 hours, two above the 48-hour allowance. The plan needs a scope or allowance decision; the new item cannot fit by labelling the old four-hour gap as six.

Material to use in your plan

Use allowance, item total, unallocated amount and overrun as separate worksheet cells. Record the decision about a gap rather than forcing numerical agreement.