Reopen a completed task with a separate rework record

Preserve the original completed output and track the specific reopened work without counting a second full delivery.

Link the defect to the original completed work

Synthetic task T-D completed a twelve-page pack. The operator later finds incorrect labels on two pages. The owner opens RW-D for those two pages and leaves the original completion evidence in history. No new pages or scope are requested.

Synthetic reopened-work record
RecordScopeCurrent state
T-D original12 pagesCompleted event retained
RW-DPages 3 and 82 pages need correction
Current packSame 12-page scopeCorrection pending
Download editable CSV ↓

Close the rework after checking corrected pages

  1. Record reported label issue
  2. Open linked two-page rework
  3. Correct named pages
  4. Check replacement pages
  5. Close RW-D and record current pack revision

A request for a thirteenth page is new scope and needs a separate decision; it is not hidden inside the two-page repair.

The project still has one twelve-page deliverable and a two-page rework task. Separate effort on RW-D from initial production effort so completion statistics do not pretend two packs were delivered.

Once RW-D closes, how many delivered packs and how many corrected pages are recorded?

Show the worked answer

One pack, with two corrected pages. The original twelve-page scope is unchanged.