Check whether a duty overlap fits the required handover

Fit a sequential briefing and access check into the intersection of two duties.

List the handover durations

Synthetic outgoing duty ends 16:00; incoming starts 15:45. Both are present during that overlap only. Handover requires a 12-minute briefing then a 6-minute joint access check; neither can run in parallel. Completing only the briefing does not complete handover.

Overlap task budget
ItemMinutesDependency
Available overlap1515:45–16:00
Briefing12First
Joint access check6After briefing
Download editable CSV ↓

Fit sequential work into overlap

  1. Find the shared presence interval
  2. Add sequential durations
  3. Compare required and available time

Do not erase the access check to make the plan fit.

How many additional overlap minutes are required?

Show the worked answer

Three:12+6=18 required against 15 available. Starting incoming duty 15:42 would provide 18 minutes if that revised window is confirmed.

Retain the unfinished check

Filled decision checks
CaseDecisionReason
Incoming 15:45Short 3 min18 required versus 15
Confirmed incoming 15:42Fits exactly18 shared minutes
Download editable CSV ↓

Record a confirmed revised start or a separately authorised handover arrangement. Until then the access check remains unplanned, not silently completed.