Compare a sparse dependency graph with an all-pairs assumption.

Plan from the supplied facts

Fictional components are A,B,C,D. Actual undirected interface links are A–B, B–C and C–D: three. The possible all-pairs count is six, but the other three are not planned. Each actual link is separately estimated at 2 hours.

Editable original planning example
Link setLinksHours at 2 per link
Actual A–B,B–C,C–D36
Additional all-pairs A–C,A–D,B–D36 not planned
All six pairs612 if actually required
Download editable CSV ↓

Work through the choice

Four components do not imply four interfaces or six implemented links. The work unit is a declared interface edge, and direction or separate operations may change that unit.

If A–D is added, what is the revised link estimate?

Show the worked answer

Four actual links ×2=8 hours. It remains below the six-link all-pairs plan.

Material to use in your plan

Use a unique endpoint-pair register for the stated undirected model, then estimate each declared edge. Add direction and operation scope if the actual integration requires them.