Estimate work from a crossed coverage matrix

Count planned combinations before applying effort per combination.

Plan from the supplied facts

Fictional plan explicitly checks every combination of two interfaces, three roles and four record scenarios. Each combination is budgeted at 0.5 hour, with no shared setup in this estimate. This is a full Cartesian plan; whether fewer checks suffice needs a different coverage decision.

Editable original planning example
InterfaceRolesScenarios per roleCombinations / hours
I13412 / 6
I23412 / 6
Total2 interfaces3 × 4 each24 / 12
Download editable CSV ↓

Work through the choice

Adding 2+3+4 counts labels, not work combinations. The effort basis is the crossed tuple, so 2×3×4=24.

A fourth role is included on both interfaces. What is the new estimate?

Show the worked answer

2×4×4=32 combinations; 32×0.5=16 hours. The addition is eight combinations and four hours.